Older homes that need work are often the best value on the coast, because most buyers walk out when they see the kitchen. The plots and views in urbanisations from the 1980s and 1990s are often better than anything built since. Whether a renovation works out depends on three things you can control: the paperwork with the town hall, who does the work, and how you pay them.
The numbers
| Minor works | declaración responsable at the town hall; work can start once it is filed |
| Major works | licencia de obra with an architect’s project; months, varies by town hall |
| Construction tax (ICIO) | up to 4% of the works budget; each town hall sets its rate |
| IVA on renovating a home | 10% if the home is over two years old and the builder’s materials are under 40% of the cost; otherwise 21% |
| Full renovation of a flat, standard finishes | roughly 450 to 750 euros per m2 in the Marbella area (quote portals, 2026) |
| High specification | 1,000 euros per m2 and up, before pools, gardens and structural work |
Should you buy to renovate?
Work out one number before you make an offer: what does the finished home sell for? Then subtract what you pay for it and what the works really cost.
Say a 1990s villa in Bel Air is for sale at 900,000 euros and needs 250,000 euros of work. If renovated villas in the same urbanisation sell for 1,400,000, there is room for the costs, the taxes and the surprises. If they sell for 1,150,000, you are doing the work for nothing. Asking prices are not enough for this. You want what similar homes actually sold for.
Our post on why good new builds are scarce explains why a well renovated older home can compete with a new one.
Which permission do you need?
Andalucía’s land law of 2021 (the LISTA) and each town hall’s ordinances split works into two groups.

Minor works (obra menor). A new kitchen or bathrooms, flooring, painting, replacing windows like for like, new installations inside the home. These usually go through a declaración responsable: you file a statement with the town hall describing the works, and you can start once it is filed. The town hall can inspect afterwards.
Major works (obra mayor). Anything structural, an extension, a new pool, changes to the roof, the facade or the volume of the building. These need a licencia de obra mayor, applied for with a technical project signed by an architect. Expect it to take months. Times vary a lot between town halls, and anything near the coast, in a protected area or on a plot with planning problems takes longer. Ask the town hall’s planning department what it is taking at the moment.
Check the existing house before you buy. If it has an extension or a pool that was never licensed, the town hall can refuse new permissions until that is sorted out. Our post on the four checks before you buy explains how your lawyer compares what is built with what is registered.
Do not start major works without the licence. Town halls on this coast inspect, stop works and fine owners. The fees and the construction tax (the ICIO, which by law cannot exceed 4% of the works budget) are a small part of the total.
Who you need
An architect. Required for major works, and useful for anything beyond a cosmetic refresh. The architect draws the project, applies for the licence and directs the works. Fees are agreed freely, so ask for a written fee proposal that says what is included.
A technical architect (aparejador). Directs the work on site and is responsible for health and safety. Often part of the architect’s team.

A builder. A registered business with liability insurance that can invoice with IVA. Ask for the last three jobs and go and see one. Good builders on the coast are usually booked ahead, so a builder who can start next Monday is worth a second question.
Someone on site, if you are not. If you live abroad during the works, someone has to check progress, approve stage payments and deal with changes. That can be the architect, an independent project manager, or a person you trust locally. A site its owner visits once a month tends to run on the builder’s other priorities.
How to pay
Most renovation horror stories come down to the same thing: too much money paid too early.
- Keep any upfront payment small. A deposit for materials is reasonable. Half the budget before work starts is not.
- Pay against finished stages. The contract lists the stages (demolition, structure, installations, finishes) with a price for each. The architect or project manager confirms each stage is done before you pay for it.
- Keep a retention. Hold back 5% to 10% until the snagging is finished and, ideally, until the first winter has shown whether the roof and terraces keep the rain out.
- Agree every change in writing, with a price, before it is done. Budgets usually double through many small verbal changes rather than one big one.
What it costs
Quote portals that collect real builders’ estimates put a full renovation of a flat in the Marbella area at roughly 450 to 750 euros per square metre with standard finishes in 2026, and 1,000 euros or more for high specification. Those figures cover labour and materials, not the licence, the architect or the IVA. Villas cost more per square metre than flats because of the roof, the terraces and the outside space, and structural work, pools and gardens come on top.
Use these figures to check whether a project is in the right range, not to set a budget. Get three detailed written quotes for the actual house, and add a contingency for what you find behind the walls. On older homes, it is usually needed.
On IVA: works to renovate a home qualify for 10% instead of 21% when the home was finished more than two years ago, you are a private owner using it as a home, and the materials the builder supplies are under 40% of the total. The builder’s invoice has to apply the right rate.
How long it takes
Minor works usually take weeks. Major works take months for the licence and then months for the build. Then come the delays nobody plans: the builder’s last job running late, a material on back order, a problem inside a wall. On a first renovation here, plan for it to take longer than you are told.
Our Cancelada case shows a full refurbishment of an inherited townhouse, done once the legal problems with it had been solved.
Sources: Ley 7/2021 de Impulso para la Sostenibilidad del Territorio de Andalucía (LISTA) on licences and declaraciones responsables; Real Decreto Legislativo 2/2004 (local finance law), article 102, on the 4% ICIO ceiling; Ley 37/1992 del IVA, article 91.Uno.2.10º, on 10% IVA for home renovations; Ley 38/1999 de Ordenación de la Edificación on projects and site direction; Cronoshare, Habitissimo and hacecuentas.com renovation price estimates for Málaga province, 2026.
Frequently Asked Questions
Do I need a licence to renovate a property in Spain?
You need to file something before you start. In Andalucía, minor works such as kitchens, bathrooms and floors usually need a declaración responsable. Structural works, extensions, pools and changes to the roof or facade need a licencia de obra mayor with an architect’s project.
How much does it cost to renovate a home on the Costa del Sol?
Quote portals put a full renovation of a flat in the Marbella area at roughly 450 to 750 euros per square metre with standard finishes in 2026, and 1,000 or more for high specification, before the licence, architect and IVA. Villas cost more. Get three written quotes.
What is the IVA on renovation work in Spain?
10% when the home is more than two years old, the owner is a private person using it as a home, and the builder’s materials are under 40% of the cost. Otherwise 21%.
How should I pay a builder in Spain?
A small deposit for materials, then payments against finished stages confirmed by the architect or project manager, with 5% to 10% held back until the snagging is done. Never half upfront.
Can I renovate while living abroad?
Yes, if someone on the ground checks the stages, approves changes and reports to you. That can be the architect, a project manager or someone you trust.
How much is the construction tax (ICIO)?
Each town hall sets its own rate, up to a legal maximum of 4% of the works budget. It is paid with the licence or the declaración responsable.